Construction Bulletin: Ground Penetrating Radar Survey Work

Beginning on Thursday July 12, and lasting for about three weeks, the NYCDOT Division of Bridge’s contractors will conduct ground penetrating radar survey work along the Brooklyn Heights Promenade in preparation for the future rehabilitation of the Brooklyn-Queens Expressway, Atlantic Avenue to Sands Street. This weather dependent operation will help inform the project team of existing conditions underground and will take place between the hours of 8:00 a.m. and 4:00 p.m. from Monday to Friday.

The promenade will remain open at all times.

Throughout the duration of this work, promenade users can expect to see a device similar to the one in the attached notice. All operators of the device will wear safety vests.

This work is being conducted under a permit issued by and in close coordination with the Department of Parks and Recreation. Any damaged vegetation will be replaced.

For any questions or inquiries please contact The BQE Project Team at 332-999-4520 or [email protected].